How Buying Preconstruction Works in Florida, Step by Step

A plain walkthrough of a Florida preconstruction condo purchase, from reservation to closing, and the statutory disclosures that apply along the way.

Buying a residence before it is built is a different transaction from buying one that exists. You sign a contract against plans, floor plans and a set of legal documents, and you close months or years later, when a local building authority certifies the building is complete. Florida regulates the condominium version of this process closely. This guide walks through the sequence a buyer typically follows and points to the statutes that apply at each step.

Step 1: Reservation

Some projects begin with a reservation agreement, which holds a unit while the sales documents are finalized. Florida law treats the money differently from a purchase deposit. Under Fla. Stat. 718.202(6), a developer that takes reservation deposits must place them in escrow, and a buyer can ask for a full, unconditional refund at any time before a purchase agreement is signed. Once the purchase agreement is signed, the deposit falls under the rules for sales deposits.

Step 2: Receive the disclosure documents

A developer of a residential condominium with more than 20 units must prepare a prospectus or offering circular and file it with the Division of Florida Condominiums, Timeshares, and Mobile Homes before entering an enforceable contract (Fla. Stat. 718.504). A copy goes to each buyer. Under the statute it includes a description of the buildings and units, the estimated completion date, use restrictions, management arrangements, an estimated operating budget, and exhibits such as the declaration, articles of incorporation, bylaws and floor plans. The budget must carry a statement that it is a good-faith estimate only.

The document is a summary. Read the exhibits, particularly the declaration and the budget, because they set what you can do in the unit and what you will pay each month.

Step 3: Sign the contract and start the 15-day clock

Under Fla. Stat. 718.503, a developer’s contract for a residential unit must contain a conspicuous legend stating that the buyer may cancel by written notice within 15 days after signing and after receiving all required documents. The first page must also carry a caution that oral representations cannot be relied upon. The statute provides that a purported waiver of these voidability rights has no effect, and that the right to void ends at closing. If the developer has not delivered the required documents, the buyer may void the contract and receive the deposit back.

Step 4: Pay deposits into escrow

Payments up to 10 percent of the sale price must go into an escrow account under Fla. Stat. 718.202(1). Amounts above 10 percent go into a special escrow account and generally may not be used before closing, with a narrow exception: if the contract allows it, and construction has begun, the developer may draw on those excess funds for actual construction and development costs. A contract that permits this must say so in a bold legend. The next article in this series covers deposits in more detail.

Step 5: Wait for construction

During construction your contract and the developer’s filings govern what happens. If the developer amends its offering in a way that materially and adversely affects you, section 718.503 gives you a new 15-day window from receipt of the amendment. The statute defines “completion of construction” for deposit purposes as issuance of a certificate of occupancy for the entire building, or substantial completion where no certificate is issued.

Step 6: Inspect and close

Before closing, buyers and builders typically do a walkthrough to list cosmetic defects, missing items or departures from the contract. According to Barnes Walker, a Florida title services firm, closing on new construction is tied to the certificate of occupancy rather than a fixed date, and an escrow holdback can be negotiated when finishing work cannot be completed before closing. A walkthrough is common practice, not a statutory requirement.

After closing, section 718.203 provides statutory warranties from the developer. A unit is warranted for three years from completion of the building containing it, and the roof, structural components and building mechanical, electrical and plumbing elements carry their own term, capped at five years.

Townhomes and single-family homes

Where a new community is governed by a homeowners’ association rather than a condominium association, Fla. Stat. 720.401 requires a disclosure summary before you sign. If it is not provided in advance, the buyer may cancel by written notice within 3 days after receiving it, or before closing, whichever comes first.

What to check before you buy

  • Confirm the contract contains the 15-day legend and the escrow agent’s name.
  • Read the prospectus exhibits, especially the declaration and the budget.
  • Ask who holds your deposit and under what terms funds above 10 percent may be used.
  • Find the stated completion date and what the contract says if it slips.
  • Have a Florida real estate attorney review the contract before you sign.

This article is general information, not legal advice. Statutes change; confirm the current text and your own contract with a licensed Florida attorney.